Soluna Briscoe AI Campus: Fiber and RFP Watch

Soluna Holdings has signed a definitive agreement with Applied Digital to develop a planned 50 MW critical-IT data center for AI and high-performance computing at Project Dorothy 3, about five miles south of Silverton in Briscoe County, Texas. The first phase would sit next to Soluna’s existing Dorothy 1 and 2 sites and the 150 MW Briscoe Wind Farm, inside a proposed county reinvestment zone of about 403 acres whose improvements, including business personal property, are estimated at more than $8 billion. The joint venture has not closed, a ChronoScale lease is still non-binding, and as of Nov. 12 the outcome of Briscoe County’s Nov. 9 tax-abatement hearing had not been posted. Here is what the filings and county records say, and what telecom and fiber teams should watch next.