Soluna Holdings and Applied Digital have agreed to form a jointly owned company to develop a planned 50 MW critical-IT data center for AI and high-performance computing at Project Dorothy 3, near Silverton in Briscoe County, Texas. The site sits about five miles south of town along Highway 207, next to Soluna’s existing Dorothy 1 and 2 campuses and across from the substation for the 150 MW Briscoe Wind Farm, which Soluna bought in April. A first 50 MW phase is the only capacity covered by the October joint-venture agreement. Soluna has separately described Dorothy 3 as a campus with potential capacity of up to 300 MW.
This is still a pre-closing development story, not a started construction job with a published delivery date. For telecom carriers, fiber optic providers and broadband sales teams that work the Texas Panhandle, it is worth putting on a watch list now—especially the rural backhaul question a 50-to-300 MW AI campus would raise in a county of fewer than 1,500 people.
What Soluna and Applied Digital announced in October
According to Soluna’s Oct. 21, 2026 release and the company’s same-day Form 8-K describing a Subscription Agreement dated Oct. 20:
- Project: a planned 50 MW critical-IT data center for AI and HPC at Project Dorothy 3, Soluna’s development site near Silverton (Briscoe County) and the Briscoe Wind Farm.
- Ownership after closing: Applied Digital, through affiliates, is expected to hold a 51% interest in the project company, STX JV Holdings LLC. Soluna is expected to hold the remaining 49%. Soluna would contribute a portion of the Dorothy 3 site, including land and power-related project assets. Applied would provide capital. The 8-K values Soluna’s ground-sublease contribution at $18.75 million and Applied’s cash contribution at $19,515,306, subject to a dollar-for-dollar credit for development work or long-lead equipment Applied or its affiliates pay for before closing.
- Tenant interest, not a signed lease: ChronoScale Holdings Corporation (Nasdaq: CHRN), a company majority-owned by Applied, has signed a non-binding letter of intent for a triple-net lease of the planned facility. Soluna’s release and 8-K both say a definitive lease remains subject to negotiation, execution and ChronoScale’s internal approvals. There is no assurance a lease will be signed on the terms in the letter of intent, or at all.
- Closing conditions and timing: closing is expected on or before Dec. 1, 2026, and is conditioned on a Briscoe County tax-abatement vote, title insurance, corporate approvals, and execution of an operating agreement, definitive leases, power agreements and other ancillary agreements that had not been finalized as of the 8-K. If the tax-abatement vote is the only open item, the outside date extends automatically by 30 days; a title delay can extend it by 10 days. In no event does the outside date extend beyond Dec. 31, 2026. If the agreement is terminated, Soluna would be obligated to reimburse Applied for 80% of certain funded development costs, up to $45 million.
- Operating entity: at closing, STX-01 LLC, a wholly owned subsidiary of the project company, is expected to take a 99-year ground sublease and serve as landlord under the contemplated data-center lease.
This draft did not find a standalone Applied Digital press release or Applied 8-K covering the same transaction. The terms above come from Soluna’s release and Soluna’s Form 8-K, which names Applied affiliates as parties to the agreement.
The site: 397 acres purchased, a 403-acre zone
On Aug. 24, 2026, Soluna said it had closed the purchase of 397 acres in Briscoe County to host Project Dorothy 3. The same-day Form 8-K furnished that release. Soluna said the parcel sits adjacent to Projects Dorothy 1 and 2 and to the 150 MW Briscoe Wind Farm, with the wind farm’s substation “directly across from the acquired property,” positioning Dorothy 3 for behind-the-meter access to generation Soluna owns. The 397 acres, Soluna said, exceeded the 300 acres it had originally identified and left room for additional data halls if more generation or storage became available.
Soluna’s project page describes Dorothy 1A and 1B as a 50 MW operating Bitcoin hosting and mining campus and Dorothy 2 as an adjacent 48 MW expansion, also used for Bitcoin hosting and mining. Dorothy 3 is listed there as a planned renewable-powered AI campus. Those existing sites are already in operation; the October agreement covers a new AI/HPC phase, not a conversion of Dorothy 1 and 2.
Briscoe County’s notice of public meeting describes a slightly larger tract: 403.397 acres more or less, in all or portions of Sections 7 and 14, Block B-2, BS&F, RY, about five miles south of the City of Silverton along Highway 207, in the vicinity of the existing Soluna “Dorothy” data center. The notice names the landowners as Soluna Dorothy 3 Energy ServiceCo. LLC and Soluna DV BNSF Energy HoldCo. LLC, identified as subsidiaries of “Soluna Energy, Inc.” The publicly traded parent that issued the press releases and 8-Ks is Soluna Holdings, Inc. (Nasdaq: SLNH). The two acreage figures should not be collapsed into one: 397 acres is the August land purchase Soluna announced; about 403 acres is the tract described in the county reinvestment-zone notice.
The $8 billion figure is a zone estimate, not a 50 MW contract price
The same county notice says the estimated value of the improvements in the proposed zone, including tangible business personal property, is more than $8,000,000,000. That is a county estimate for the zone as a whole—one or more data centers, ancillary facilities, and equipment. It should not be read as the construction contract value for the initial 50 MW facility, as Applied Digital’s roughly $19.5 million closing cash contribution, or as a disclosed capital budget for a 300 MW build-out. Soluna has not published a campus construction cost or a ready-for-service schedule for Dorothy 3.
The notice frames the county action as a proposed designation of Reinvestment Zone #6 and possible property-tax abatement under Chapter 312 of the Texas Tax Code, on applications by STX-01 LLC and/or its affiliates. The Nov. 9, 2026 Commissioners Court agenda uses a different zone label: a public hearing and possible order designating Reinvestment Zone No. 2026-07, and a possible tax-abatement agreement with Soluna Energy, Inc., through affiliates and subsidiaries, for qualified property associated with the Dorothy 3 project. This post uses both labels as they appear in the county documents and does not treat them as confirmed to be the same instrument until the court posts an adopted order.
This is a local Chapter 312 process, not a Texas Jobs, Energy, Technology and Innovation (JETI) / Chapter 403 agreement. A review of the Comptroller’s current JETI agreements list on Nov. 12 did not show a Soluna, STX-01 or Dorothy 3 filing.
Separately, the Texas Comptroller’s registered qualifying data centers list includes Project Dorothy 3A, effective Sept. 8, 2026, with STX-01 LLC as owner and operator and Chronoscale Corporation as occupant. That listing is part of the state’s data-center sales-and-use tax program. It is not a substitute for the county abatement vote, and it does not by itself mean a lease or the joint venture has closed.
The county already posts an earlier tax-abatement agreement with Soluna DV Services, LLC, in phases. That record relates to Soluna’s prior Briscoe County activity and should not be assumed to be the Dorothy 3 agreement listed on the November agenda.
Power: a 150 MW wind farm and the ERCOT grid
Soluna closed the purchase of the 150 MW Briscoe Wind Farm on April 1, 2026, for $53 million, according to the company’s April 2 release. The release describes GE Vernova turbines and an ERCOT substation and grid interconnection. In that announcement, Soluna already pointed to a Dorothy 3 campus of up to 300 MW on land adjacent to Dorothy 1 and 2, and said the expansion was expected to come from continued grid-interconnection work and onsite generation.
The October release is more specific about Phase 1: subject to definitive documentation, the 50 MW critical-IT phase “is expected to draw power from both Briscoe Wind and the grid.” Headlines that call the project strictly wind-powered overstate what Soluna has actually said. Definitive power agreements were still to be negotiated as of the Oct. 21 8-K, and no interconnection-upgrade schedule for a 300 MW campus has been published in the materials reviewed for this draft.
Population: the county is about 1,500; Silverton is much smaller
The viral framing of an “$8 billion data center” in a “county of just 1,500 people” is directionally right about the county and wrong if it is read as the population of Silverton itself.
The U.S. Census Bureau’s QuickFacts for Briscoe County puts the 2020 Census population at 1,435 and the July 1, 2025 estimate at 1,474. Silverton, the county seat, is far smaller. The Bureau’s Vintage 2025 city and town estimates file lists Silverton city’s April 1, 2020 estimates base as 627 and its July 1, 2025 population as 639. The 1,500-person figure is a rounded county total, not the town.
The same QuickFacts table says 73.1% of Briscoe County households had a broadband internet subscription in 2020–2024. That is a household figure. It is not a measure of diverse, high-capacity fiber to a planned AI campus five miles south of town.
The Nov. 9 hearing: scheduled, outcome not yet posted
Briscoe County noticed a regular Commissioners Court meeting for Nov. 9, 2026, at 9:00 a.m. in the Commissioners Courtroom in Silverton, or any regularly scheduled meeting thereafter, to consider the zone designation and possible abatement agreements. The posted agenda includes a public hearing on the proposed zone, a possible designation order, an executive session on economic development, and a possible vote on a Chapter 312 tax-abatement agreement for the Dorothy 3 project.
As of Nov. 12, 2026, that outcome was not in the public record reviewed for this draft. The county’s public notices page lists a Nov. 9 agenda and a Nov. 10 canvass agenda, but the posted 2026 minutes run only through Sept. 28. A direct request for a Nov. 9 minutes file at the county’s usual upload path returned no document. The notice itself allowed the court to act on Nov. 9 or at a later regular meeting. Until minutes, an adopted order or an executed agreement are posted, the abatement should be described as pending, not approved or denied.
The Caprock Courier covered a packed Oct. 2 town hall on the proposal and reported county-budget and job claims from that meeting. Those are local-paper accounts of a company presentation, not a substitute for a recorded court vote.
What telecom and fiber teams should watch
A 50 MW AI hall, let alone a campus Soluna has described as having up to 300 MW of potential, does not show up only in a tax-abatement notice. It also changes the demand picture for fiber optic and broadband infrastructure in a thinly populated Panhandle county.
Backhaul and middle-mile in the Silverton / Highway 207 corridor. Hyperscale or AI campuses typically need diverse, high-capacity routes to carrier hotels, internet exchanges and long-haul paths out of the region. Dorothy 3 would sit about five miles south of Silverton, next to two already operating Soluna sites, which may mean some on-site power and access infrastructure already exists—but neither Soluna nor Applied Digital has published carrier names, route maps, fiber counts or meet-me points for the new AI phase. Providers with lit or dark fiber in Briscoe County, along Highway 207, or on paths toward Amarillo and Lubbock should map proximity to the Dorothy campus before treating the site as out of market. Rural last-mile coverage in the county, including cooperative fiber in parts of the Caprock, is a different question from diverse long-haul into an AI data hall.
Construction RFQs and adjacent public demand. The October 8-K says development work at the site has begun and may continue through closing, and that certain long-lead equipment may be procured at Applied’s expense. That is early fieldwork, not a disclosed EPC award or a building schedule. If the joint venture closes and construction proceeds, projects of this type often generate RFQs for outside-plant fiber, conduit, splice work and temporary construction connectivity, then later for permanent diverse laterals and campus interconnect. Nearby schools, libraries and clinics may also drive E-Rate, RHC, state broadband or municipal RFP notices. GIS mapping of fiber against the Highway 207 site remains the practical screen before a bid.
Watch the documents, not the headline numbers. The $8 billion-plus figure is a county estimate of zone improvements and equipment, not a signed construction price. The only capacity in the October agreement is 50 MW, with a non-binding tenant letter of intent. The 300 MW figure is Soluna’s stated campus potential, subject to generation, interconnection and later development. Closing itself still depends on a tax-abatement vote, final ancillary agreements and other conditions, with a year-end outside date. Price circuits and crews on firm RFQs and filed agreements, not on a single investment headline.
How to watch the corridor with Map4
Pin the Silverton / Briscoe County / Highway 207 corridor on the Map4 National Map, score nearby fiber providers by nearest route or coverage, and overlay open telecom RFPs—including E-Rate, state, federal and organic—so your team sees opportunities in proximity to the site as they appear.
Key dates
- April 1, 2026: Soluna closes purchase of the 150 MW Briscoe Wind Farm for $53 million — Soluna April 2 release
- Aug. 24, 2026: Soluna closes purchase of 397 acres for Project Dorothy 3 — Soluna release and Form 8-K
- Sept. 8, 2026: Texas Comptroller lists Project Dorothy 3A (STX-01 LLC / Chronoscale Corporation) as a qualifying data center — Comptroller data-center list
- Oct. 20, 2026: Soluna and Applied Digital affiliates sign the Subscription Agreement for a 50 MW Phase 1 joint venture — Soluna Form 8-K
- Oct. 21, 2026: Soluna announces the Applied Digital partnership and ChronoScale letter of intent — Soluna release
- Nov. 9, 2026: Briscoe County Commissioners Court scheduled a public hearing and possible votes on a reinvestment zone and Chapter 312 abatement; as of Nov. 12, minutes and an adopted decision were not posted — county notice and agenda
- On or before Dec. 1, 2026 (outside date no later than Dec. 31): targeted closing of the joint venture, subject to the tax-abatement vote and other conditions — Soluna Form 8-K
Sources
- Soluna, Oct. 21, 2026: partnership with Applied Digital for a 50 MW AI data center at Project Dorothy 3
- Soluna Form 8-K, Oct. 21, 2026 (Subscription Agreement dated Oct. 20)
- Soluna Form 8-K, Oct. 21, 2026 (Exhibit 99.1 press release furnished under Item 7.01)
- Soluna, Aug. 24, 2026: closes purchase of 397 acres for Project Dorothy 3
- Soluna Form 8-K, Aug. 24, 2026
- Soluna, April 2, 2026: closes $53 million acquisition of the 150 MW Briscoe Wind Farm
- Soluna project pages for Dorothy 1, Dorothy 2 and Dorothy 3
- Briscoe County Notice of Public Meeting (Reinvestment Zone #6 / Chapter 312)
- Briscoe County Commissioners Court agenda, Nov. 9, 2026
- Briscoe County public notices, agendas and minutes
- Texas Comptroller: registered qualifying data centers (Project Dorothy 3A, effective Sept. 8, 2026)
- Texas Comptroller: current JETI agreements (no Soluna / STX-01 / Dorothy 3 listing as of Nov. 12, 2026)
- U.S. Census Bureau QuickFacts: Briscoe County, Texas
- U.S. Census Bureau, Vintage 2025 city and town population estimates (sub-est2025)
- Caprock Courier, Oct. 7, 2026: town hall coverage of Project Dorothy 3